Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 21 question 36 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 36
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

As part of the 'authorize a work package' activity, the project manager is preparing the work package for the marketing materials. The project manager has asked the team manager for this work package to draft some specialist sections of the work package. The project manager and project assurance will review these sections before the work package is authorized.
Is this an appropriate action, and why?

  • A. Yes, because project assurance is responsible for the work package being correctly authorized
  • B. Yes, because the project manager is responsible for authorizing the work package even if its preparation is delegated
  • C. No, because the project manager should produce the work package as part of the 'authorize a work package' activity
  • D. No, because the team manager should approve the work package once authorized by the project manager
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Yes, because the project manager is responsible for authorizing the work package even if its preparation is delegated
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...