Which 2 alternative actions apply to the proposed supplier assurance for this project?
A.
Retain because he has a professional facilities qualification and so is in a position to specify the needs of his division.
B.
Retain because he will be able to advise on many of the products that will enable outsourcing to happen, such as the 10-year outsourcing service contract.
C.
Retain because he is well-regarded within the Ministry because of the efficiencies, superb service and savings he has achieved in the Facilities Division.
D.
Add 'Outcome Account Manager' because he will advise on potential changes and their impact on the integrity of the project's products.
E.
Remove because he is involved with the project and is therefore NOT independent.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 1 month ago