During stage 3 the 'amended course booking procedures' are being delivered using an agile delivery approach. The work package has a fixed time and cost.
There are three sprints during the stage and the prioritized products will be handed over in a phased manner throughout the stage. As part of the 'report management stage end' activity, the project manager identified some follow-on action recommendations relating to the maintenance of the booking procedures that had been handed over.
Is this an appropriate action, why?
mcesarlara
4 months, 1 week agoravi_aws
1 year, 1 month ago