Exam PRINCE2-Practitioner topic 21 question 43 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 43
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

During stage 3 the 'amended course booking procedures' are being delivered using an agile delivery approach. The work package has a fixed time and cost.
There are three sprints during the stage and the prioritized products will be handed over in a phased manner throughout the stage. As part of the 'report management stage end' activity, the project manager identified some follow-on action recommendations relating to the maintenance of the booking procedures that had been handed over.
Is this an appropriate action, why?

  • A. Yes, because time and cost are fixed therefore scope should be prioritized and flexed
  • B. Yes, because the users have taken on ongoing ownership of the products handed over
  • C. No, because the project manager should ensure that all planned products have been created
  • D. No, because the user acceptance should have been obtained at the end of each of the sprints
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mcesarlara
4 months, 1 week ago
Selected Answer: B
D. Incorrect. While user acceptance should indeed be obtained at the end of each sprint, identifying follow-on action recommendations is still appropriate and necessary. This ensures that there is a plan for ongoing maintenance and support for the products delivered. B. Correct. In an agile approach, products are often handed over incrementally, and users start using and maintaining them as soon as they are delivered. Identifying follow-on actions for maintenance aligns with ensuring that the products continue to deliver value post-project and that users are aware of their responsibilities.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
The answer is B. Yes, because the users have taken on ongoing ownership of the products handed over. In PRINCE2, the ‘Report Management Stage End’ activity involves reviewing the stage and documenting lessons learned, including any follow-on action recommendations. In this case, the Project Manager has identified some recommendations relating to the maintenance of the booking procedures that had been handed over. This is an appropriate action because it ensures that any necessary actions for maintaining the delivered products are clearly communicated to those who will be responsible for them after the project ends.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...