Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 21 question 40 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 40
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

The following risk has been recorded in the risk register:
"Because the 'e-learning course' is based on the 'classroom-based training materials', there is a risk that the materials may not be suitable for an e-learning environment, which could lead to a significant rewrite of the materials, increasing cost and time."
The risk has a high probability and impact. An appropriate 'reduce' response has been approved that aims to develop the 'classroom-based training materials' so that they are more likely to be suitable for e-learning.
What is the NEXT step to ensure effective management of the risk, and why?

  • A. Appoint a risk actionee on the team plan, because the risk response needs to be implemented when delivering the work package
  • B. Appoint a risk actionee on the team plan, because risk responses should balance the cost of the response against the impact of the risk occurring
  • C. Monitor the risk on the risk register, because the risk owner should be responsible for monitoring and controlling the risk
  • D. Monitor the risk on the risk register, because the team manager should report on risks via checkpoint reports
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
A. Appoint a risk actionee on the team plan, because the risk response needs to be implemented when delivering the work package. The reason is that according to the PRINCE2 risk management process, after planning a risk response, the next step is to implement it. This requires assigning a risk actionee who is responsible for carrying out the risk response activities and reporting on their progress. The risk actionee should be identified on the team plan, which is a document that describes how the work package will be delivered by the team manager and the team members. The team plan should also include the details of the risk response, such as the actions, resources, costs, and timescales involved.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...