Exam PRINCE2-Practitioner topic 21 question 38 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 38
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

DRAG DROP -

DIRECTING A PROJECT -
Here are three actions that are carried out as part of the 'directing a project' process.
During which activity (A-E) should the action occur?
Choose only ONE activity for each action. Each activity can be used once, more than once, or not at all.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
1.The act of approving a specific request for a communications expert to assist with the communication management approach is more of an ongoing activity that could occur at any point in the project, not just at the start of a new stage. This is why it falls under "give ad-hoc direction"
upvoted 1 times
ravi_aws
1 year, 1 month ago
2. Closure 3.It’s about advising the project manager of a change in ABC company’s approach to course delivery. This seems to be more of an ongoing guidance or direction provided to the project manager, rather than a formal authorization of a new stage or exception plan so ad-hoc direction for point 3.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.