CLOSING A PROJECT -
The project is in the 'closing a project' process and the pilot courses have been delivered. The project manager has updated the sales forecast for the health and safety training course based on the results from the 'delivered pilot courses'.
Who should approve the revised sales forecast?
ravi_aws
1 year, 1 month ago