Question #: 32
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

ABC Company's development team are using an agile delivery approach to produce the 'classroom-based training materials'. They have asked if their existing product owner can also act as team manager for their work package, although the team will continue to organize its own work within delegated limits of authority.
The project manager has agreed to this request.
Is this an appropriate action, and why?

  • A. Yes, because the product owner can also act as team manager while allowing the team to self-organize
  • B. Yes, because agile teams need to be empowered by the use of management by exception
  • C. No, because the team manager is responsible for managing the work of project team members
  • D. No, because the product owner should represent the wider view of the customer in cross-functional projects
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://prince2agile.wiki/principles/manage-by-exception/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
The answer is D. No, because the product owner should represent the wider view of the customer in cross-functional projects. According to the PRINCE2 wiki, the product owner and the team manager have different roles and responsibilities in an agile team. The product owner is responsible for maximizing the value of the product and understanding the customer needs, while the team manager is responsible for facilitating the team’s progress and ensuring the quality of production. Having the same person act as both roles may create a conflict of interest and compromise the effectiveness of the team. Therefore, it is not appropriate to have the existing product owner also act as team manager for their work package.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...