Exam PRINCE2-Practitioner topic 21 question 30 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 30
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

The e-learning course is being delivered by an external consultancy. The project manager has included a warranty period in the contract with the consultancy to ensure that any faults in the course can be fixed after the course is in operational use. This means that the work of the external consultancy will continue post- project. The project manager has suggested that an additional step be added to the standard course development model to be used for future projects to accommodate this additional work after the project has closed.
Is this an appropriate application of the 'tailor to suit the project' principle, and why?

  • A. Yes, because the project management method used should be appropriate to the customer/supplier environment
  • B. Yes, because the project controls should be appropriate to the complexity and risk of the project
  • C. No, because the PRINCE2 project lifecycle should not include project work after the project has closed
  • D. No, because the project should be following ABC Company's standard course development model
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.prince2primer.com/set-up-the-project-controls/

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
mcesarlara
2 months, 4 weeks ago
C. No, because the PRINCE2 project lifecycle should not include project work after the project has closed In PRINCE2, project closure marks the end of all project activities, and remaining work, such as support or maintenance, is transferred to the normal operation of the organization or managed as part of another project or program. Including an additional step in the course development model to manage post-project work contradicts the principle of closing a project clearly and completely.
upvoted 1 times
...
ravi_aws
1 year ago
A The ‘tailor to suit the project’ principle in PRINCE2 allows for flexibility and adaptation to different project environments. In this case, the project manager is tailoring the standard course development model to include a warranty period, which is a part of the contract with the external consultancy. This tailoring is done to ensure that any faults in the course can be fixed after it is in operational use, which is a specific requirement of this project. Therefore, this is an appropriate application of the ‘tailor to suit the project’ principle as it aligns with the customer/supplier environment. It’s important to note that tailoring doesn’t mean omitting parts of the method but adapting it to suit the project’s environment, scale, complexity, importance, capability and risk.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...