During the initiation stage the project management team have reviewed and updated the project product description. They have created a project plan, which separates the project into management stages.
Which reason explains why this is a good application of the 'focus on products' principle?

  • A. The project manager needs to plan the work so the products can be delivered
  • B. Products should be agreed collaboratively with the users to ensure user acceptance
  • C. A project needs to be delivered management stage by management stage
  • D. Projects should focus on what is going to be delivered including the acceptance criteria
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
D is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...