Question #: 28
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

The project is now in the 'closing a project' process and the project manager is evaluating the project. The project manager has asked the team manager for the
'delivered pilot courses' to identify how many errors were found in the 'accredited classroom-based training course' during the piloting of the course. In addition, the team manager of the 'finalized materials' was asked to state how many of these errors had been fixed.
Which theme is being applied?

  • A. Quality
  • B. Progress
  • C. Change
  • D. Plans
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
https://prince2.wiki/theme/quality/

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Quality
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted