Question #: 17
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

DRAG DROP -

RISK -
The following risk has been identified during a risk identification workshop:
"Because the project is reliant on the government agency accrediting the 'classroom-based training materials' before work can continue on the project, there is a risk that the accreditation will either be withheld or delayed, leading to a delay in the overall project with associated cost implications."
Here are three items of information that will be included in the risk register about this risk.
Under which heading (A-F) should they be recorded?
Choose only ONE heading for each item of information. Each heading can be used once, more than once, or not at all.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Risk Risponse, Risk Owner, Proximity
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...