Exam PRINCE2-Practitioner topic 21 question 13 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 13
Topic #: 21
[All PRINCE2-Practitioner Edition 6 Questions]

PRINCIPLES -
The Health and Safety Training project is following ABC Company's standard course development model. The executive wants start the project as quickly as possible to exploit the market opportunities offered by the new legislation. Therefore, the executive has advised the project manager that a project brief is not required, and that the project can proceed to the initiation stage.
Is this an appropriate action for the 'continued business justification' principle, and why?

  • A. Yes, because the project is following the company's standard course development model
  • B. Yes, because the recent government legislation means there is a market opportunity to exploit
  • C. No, because every project needs some form of documented and approved business justification
  • D. No, because compulsory projects that are driven by legislation must show that the chosen option is value for money
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
C According to the 'continued business justification' principle in PRINCE2, every project needs some form of documented and approved business justification 1 3 . Therefore, it is not appropriate for the executive to advise the project manager that a project brief is not required, and that the project can proceed to the initiation stage
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...