Which 2 statements should be recorded under the Timescale heading?

  • A. Benefits will be lost if the project is not completed on time.
  • B. A recruitment campaign to fill the existing staff vacancies will need to take place in the next 12 months.
  • C. Additional 10% increase in orders in year two.
  • D. The prepared calendar pack must be delivered by the first week in December.
  • E. The print company requires a 2 week notification period of the calendar pack delivery.
Show Suggested Answer Hide Answer
Suggested Answer: CD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
The 2 statements that should be recorded under Timescale are: C) Additional 10% increase in orders in year two. D) The prepared calendar pack must be delivered by the first week in December
upvoted 1 times
ravi_aws
1 year, 1 month ago
Sorry D and E
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...