Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 18 question 45 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 45
Topic #: 18
[All PRINCE2-Practitioner Edition 6 Questions]

The Business Development Director is the senior user. She has agreed a plan for post-project benefit reviews as part of the 'evaluate the project' activity.
Is this an appropriate application of the 'closing a project' process, and why?

  • A. Yes, because there should be a review of the successes and failures of the project, with recommendations for future projects to consider
  • B. Yes, because there should be an assessment of the benefits achieved compared with those defined in the business case
  • C. No, because the senior user should check how benefits of operational products win be measured in the 'hand over products' activity
  • D. No, because it is the executive that should approve the follow-on action recommendations identified by the project manager
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
B) Yes, because there should be an assessment of the benefits achieved compared with those defined in the business case is the correct answer.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...