As part of the 'closing a project' process, an announcement is to be made that ABC Company's 'capability to deliver health and safety training' is now ready for launch and the project has been closed.
Which role should prepare the draft of the announcement?

  • A. Corporate, programme management or the customer
  • B. Executive
  • C. Senior user
  • D. Project manager
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
announcement is usually made by the Executive
upvoted 1 times
ravi_aws
1 year, 1 month ago
B - Exec
upvoted 1 times
ravi_aws
1 year, 1 month ago
But drat will be created by Project manager so right answer is PM
upvoted 1 times
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...