MANAGING A STAGE BOUNDARY -
During the 'managing a stage boundary' process at the end of stage 2, the project manager is updating the business case and needs to confirm that the aggregated risk exposure for the delivery or the stage a plan remains within the risk tolerances.
Which role should confirm that the risk exposure is acceptable as part of the 'update the business case' activity?

  • A. Executive
  • B. Senior user
  • C. Senior supplier
  • D. Project assurance
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
In the context of project management, the role that should confirm that the risk exposure is acceptable as part of the
upvoted 1 times
ravi_aws
1 year, 1 month ago
In the context of project management, the role that should confirm that the risk exposure is acceptable as part of the ‘update the business case’ activity is typically the Executive. So, the answer would be
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...