Exam PRINCE2-Practitioner topic 18 question 39 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 39
Topic #: 18
[All PRINCE2-Practitioner Edition 6 Questions]

A single work package has been created for the products of stage 2 and a team manager appointed for the whole work package. The team manager has split the work package into multiple smaller work packages for each product to be delivered in stage 2. The 'managing product delivery' process activities have been tailored so that the lower-level team managers report to the higher-level team manager.
Is this an appropriate application of the 'managing product delivery' process, and why?

  • A. Yes, because for large work packages, a team manager may create a hierarchy of smaller work packages to allocate to the team members
  • B. Yes, because activities in the 'managing product delivery' process may be split or run concurrently independent of the 'controlling a stage' process
  • C. No, because there should be a single team manager who is responsible for the delivery of the whole work package
  • D. No, because creating a single work package for all stage products will lead to conflicting responsibilities between the project manager and team manager
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
In this case, option A is the most appropriate choice because it recognizes that for larger work packages, it is common practice to break them down into smaller, more manageable work packages to improve efficiency and delegation within the team.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...