Question #: 34
Topic #: 18
[All PRINCE2-Practitioner Edition 6 Questions]

During the 'initiating a project' process the Corporate Document Manager agreed to allocate a Document Controller to support the implementation of the defined change control procedures. This role will support the change authority. The project manager documented this in the change control approach.
Is this action an appropriate application of the 'initiating a project' process, and why?

  • A. Yes, because the project manager and project assurance may act as the change authority
  • B. Yes, because the change control approach should be tailored as part of the 'initiating a project' process
  • C. No, because the Document Controller's role could conflict with the project manager's responsibilities
  • D. No, because project support roles should be agreed as part of the 'starting up a project' process
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Yes, because the change control approach should be tailored as part of the 'initiating a project' process
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...