In the project mandate ABC Company identified a business opportunity in creating an accredited health and safety training course. However, it was unclear whether ABC Company would just create the course, enabling the course to be sold to other training companies, or whether they would deliver the courses to attendees as well. This was not resolved during the 'starting up the project process'. However, the project board did agree the need to have the 'capability to provide health and safety training' and that other decisions would be taken during the initiation stage.
Is this an appropriate application of the 'starting up a project process', and why?