Exam PRINCE2-Practitioner topic 18 question 28 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 28
Topic #: 18
[All PRINCE2-Practitioner Edition 6 Questions]

During the planning for stage 2 the executive has asked the project manager to carry out a MoSCoW prioritization of the products to assist in setting scope tolerances.
Is this an appropriate application of the 'progress' theme, and why?

  • A. Yes, because the executive is responsible for advising ABC Company corporate management of appropriate project scope tolerances
  • B. Yes, because the executive is responsible for setting the permitted variation of the scope of the management stages
  • C. No, because ABC Company's corporate management should set the project scope tolerance in the project mandate
  • D. No, because scope tolerance at the stage level is used if applying an agile delivery approach
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Exec or Project board set stage level tolerances
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...