During the planning for stage 2 the executive has asked the project manager to carry out a MoSCoW prioritization of the products to assist in setting scope tolerances. Is this an appropriate application of the 'progress' theme, and why?
A.
Yes, because the executive is responsible for advising ABC Company corporate management of appropriate project scope tolerances
B.
Yes, because the executive is responsible for setting the permitted variation of the scope of the management stages
C.
No, because ABC Company's corporate management should set the project scope tolerance in the project mandate
D.
No, because scope tolerance at the stage level is used if applying an agile delivery approach
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 1 month ago