Exam PRINCE2-Practitioner topic 18 question 27 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 27
Topic #: 18
[All PRINCE2-Practitioner Edition 6 Questions]

The 'capability to deliver health and safety training' has been delivered and accepted. The project manager has produced the end stage report and has recommended that the project should be closed because it is complete.
Is this an appropriate application of the 'progress' theme, and why?

  • A. Yes, because the project product has been accepted and therefore the project should be closed
  • B. Yes, because the end stage report should recommend the next steps to take to the project board
  • C. No, because the executive should be responsible for recommending project closure to ABC Company
  • D. No, because an end stage report is not required for the stage in which the project product is delivered
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Yes, because the end stage report should recommend the next steps to take to the project board
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...