Exam PRINCE2-Practitioner topic 18 question 21 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 21
Topic #: 18
[All PRINCE2-Practitioner Edition 6 Questions]

During the initiation stage the Corporate Quality Manager advised the project manager that ABC Company's risk management tool should be used by the project.
The project manager prefers an alternative tool and has documented this in the projects risk management approach which has been approved by the project board.
Is this an appropriate application of the risk management approach, and why?

  • A. Yes, because the project board should approve the risk management approach in the 'directing a project' process
  • B. Yes, because the risk management approach should include the tools and techniques to be used for risk management
  • C. No, because the risk management approach should specify the use of the corporate risk management tool
  • D. No, because the risk management approach is approved by the project board in the 'directing a project' process
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
B. Yes, because the risk management approach should include the tools and techniques to be used for risk management
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...