Question #: 12
Topic #: 18
[All PRINCE2-Practitioner Edition 6 Questions]

The Training Development Manager is the senior supplier. Towards the end of stage 3, the Training Development Manager selected a course developer to deliver the work package for the 'finalized materials'. As a result, the project manager asked the course developer to produce a plan for this work.
Is this an appropriate application of the 'organization' theme, and why?

  • A. Yes, because the Training Development Manager is responsible for delivering at the directing' level of management
  • B. Yes, because the plan demonstrates how the product will be delivered at the 'delivering' level of management
  • C. No, because the project manager should ensure that the products are delivered at the 'managing' level of management
  • D. No, because the course developer's plan should be authorized at the 'directing' level of management
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Yes, because the plan demonstrates how the product will be delivered at the 'delivering' level of management
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...