Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 17 question 3 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 3
Topic #: 17
[All PRINCE2-Practitioner Edition 6 Questions]

Which product should show that if anybody has any remaining resource costs to be charged to the project, they should ensure this is done by 10 November?

  • A. Benefits Review Plan
  • B. End Project Report
  • C. Follow-on action recommendations
  • D. Project closure notification
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
option D is the correct choice, as the Project closure notification should include instructions for charging any remaining resource costs before the given deadline of 10 November
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...