No Benefits Review Plan has been developed. Where should the schedule of benefit reviews be recorded?
A.
As deliverables of the project, all benefit reviews should be scheduled and documented in the Project Plan during initiation.
B.
Small projects do not require a schedule of benefit reviews as only one review is required towards the end of the project and this should be documented within the Business Case.
C.
Benefit reviews should be planned and recorded in the simple PID.
Benefit reviews should be planned and recorded in the simple PID.