Question #: 4
Topic #: 16
[All PRINCE2-Practitioner Edition 6 Questions]

No Benefits Review Plan has been developed. Where should the schedule of benefit reviews be recorded?

  • A. As deliverables of the project, all benefit reviews should be scheduled and documented in the Project Plan during initiation.
  • B. Small projects do not require a schedule of benefit reviews as only one review is required towards the end of the project and this should be documented within the Business Case.
  • C. Benefit reviews should be planned and recorded in the simple PID.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Benefit reviews should be planned and recorded in the simple PID.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...