Exam PRINCE2-Practitioner topic 14 question 6 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 6
Topic #: 14
[All PRINCE2-Practitioner Edition 6 Questions]

The team member collating the list of customers has now forecast that it will NOT be complete by the end of this stage as originally planned, due to a number of new prospective customers' details not yet being available. What action should the team member take?

  • A. Report the forecast delay in the next Checkpoint Report to the Executive.
  • B. Add the product to the next Stage Plan in order to allocate additional resources and complete the work.
  • C. Make an entry in the Risk Register so the Project Manager can decide on appropriate action.
  • D. Raise an issue to inform the Project Manager.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
Raise an issue to inform the Project Manager.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...