Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 14 question 2 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 2
Topic #: 14
[All PRINCE2-Practitioner Edition 6 Questions]

During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct?

  • A. The tolerances stated in the Project Plan CANNOT be changed.
  • B. The Executive needs to seek formal approval from corporate management to implement this change.
  • C. The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register.
  • D. The revision of the Project Plan would have to wait until the end stage assessment of stage 2.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
During stage 2, if the Project Manager decides to recommend that the Project Plan is revised to finish three weeks later, which statement is correct? A. The tolerances stated in the Project Plan CANNOT be changed. B. The Executive needs to seek formal approval from corporate management to implement this change. C. The current project must close prematurely and be restarted with a new Project Plan, a new Business Case and new Risk Register. D. The revision of the Project Plan would have to wait until the end stage assessment of stage 2.
upvoted 1 times
ravi_aws
1 year, 1 month ago
B. The Executive needs to seek formal approval from corporate management to implement this change. This is because a change in the Project Plan, especially one that affects the project’s timeline, is a significant event. It can impact resources, costs, and deliverables. Therefore, such a change typically requires approval from higher management or stakeholders to ensure alignment with organizational goals and strategies.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...