ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the
Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project.
Is this an appropriate application of the 'tailor to suit the project' principle, and why?