Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 40
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

DRAG DROP -

BUSINESS CASE -
Here are three actions related to applying the business case theme.
Which role (A-F) should carry out each action?
Choose only one role for each action. Each role can be used once, more than once, or not at all.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Executive, as this role is responsible to obtain project funding. Senior User, as this role is responsible for benefit forecast and realization. Project support, as this role assists project manager in maintaining the issue register.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
1. Executive 2. Senior user 3.Project support
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...