Exam PRINCE2-Practitioner topic 11 question 35 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 35
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

The 'classroom-based training materials' will be used as the basis for developing the 'e-learning course'. As a result, the executive wants to ensure that the
'classroom-based training materials' are of the required standard. The executive has asked to meet the project manager every day during stage 2 to discuss progress and identify any concerns regarding quality.
Is this an appropriate approach to applying the organization theme, and why?

  • A. Yes, because the executive should be available to provide ad hoc direction to the project manager.
  • B. Yes, because the executive should be the key decision-maker on the project, supported by other project board members.
  • C. No, because the senior user should be responsible for specifying the quality criteria for the training materials.
  • D. No, because the project manager should be given authority to manage the project on a day-to-day basis.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: D
Agreed with the option D. Manage by exception principle gives project manager authority for day to day management of the project in all aspect.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
The answer is D. No, because the project manager should be given authority to manage the project on a day-to-day basis. While it’s important for the executive to be involved and informed about the project’s progress, daily meetings could be seen as micromanagement and may not be the most efficient use of either the executive’s or the project manager’s time.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...