Question #: 31
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

At the end of stage 2, the specialist 'e-learning course' supplier will be selected. As a result, it is decided that the quality management approach will not be created until the end of stage 2, to take into account this supplier's standards and techniques.
Is this appropriate, and why?

  • A. Yes, because the quality management approach should take into account the supplier's standards, tools and techniques.
  • B. Yes, because the product description for each product will define the required quality approach within each stage.
  • C. No, because the quality management approach should be created during the initiation stage and updated later.
  • D. No, because the quality management approach should be limited to ABC Company's quality standards.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
The answer is C. No, because the quality management approach should be created during the initiation stage and updated later. In project management, it’s important to establish a quality management approach early on. This approach outlines the organization’s quality expectations, standards, and processes that will be used throughout the project. It provides a framework for ensuring that the project’s outputs meet the required standards and deliver value to the stakeholders.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...