Question #: 26
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

The external team manager for the 'e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The 'e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.
Is this appropriate, and why?

  • A. Yes, because the project manager needs to receive confirmation that work has been completed and approved.
  • B. Yes, because a team plan to gain accreditation of the 'e-learning course' is required to be part of the work package.
  • C. No, because it is the configuration item record of the relevant product description that is updated, not the work package.
  • D. No, because the work package should be checked to confirm the reporting arrangements of the 'e-learning course'.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
11 months, 2 weeks ago
Selected Answer: A
Refer 18.4.3 During 'Deliver A Work Package' the TM is responsible for updating both the 'Work package' & 'Team Plan' and also for activity 'Notify the project manager that the work package is complete'.
upvoted 1 times
...
Merv49
1 year ago
Selected Answer: B
correct
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
The correct answer is A. Yes, because the project manager needs to receive confirmation that work has been completed and approved. In PRINCE2, once a work package is completed, the team manager is responsible for updating the work package status and notifying the project manager. This ensures that the project manager is aware of the progress and can update the stage plan and project plan accordingly. In this scenario, the team manager has appropriately updated the work package and team plan after ensuring all quality activities have been completed and the ‘e-learning course’ has been approved and accredited
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...