Exam PRINCE2-Practitioner topic 11 question 22 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 22
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

An external consultant has signed a contract and agreed a work package to accredit the trainers. The Purchasing Manager will monitor the contract, which states the requirement to organize the accreditation with the Training Delivery Manager. The Training Delivery Manager has tried to contact the consultant but there has been no response. The project manager believes there is a risk that the consultant is prioritizing other clients' work.
The Purchasing Manager has been assigned as the risk owner. Is this an appropriate approach to managing this risk, and why?

  • A. Yes, because the Purchasing Manager is monitoring the contract and therefore best suited to controlling the risk.
  • B. Yes, because the Purchasing Manager should have identified the risk when the work package was agreed.
  • C. No, because the team manager should be the risk owner to risks concerning the delivery of a work package.
  • D. No, because the risk was transferred to the Training Delivery Manager when the work package was authorized.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
The correct answer is A. Yes, because the Purchasing Manager is monitoring the contract and therefore best suited to controlling the risk. In PRINCE2, a risk owner is the individual responsible for managing a particular risk. In this scenario, the Purchasing Manager is monitoring the contract with the external consultant who is responsible for accrediting the trainers. Therefore, they are in a good position to control and manage the risk associated with the consultant potentially prioritizing other clients’ work. They can monitor the situation, communicate with the consultant, and take necessary actions if needed.
upvoted 1 times
ManikRoy
1 year, 1 month ago
Agreed.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...