Exam PRINCE2-Practitioner topic 11 question 21 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 21
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

ABC Company carried out a similar project two years ago, in response to changes in health and safety legislation for the health service. The experiences from that project were used to refine the corporate risk management policy. For that reason, the project board decided to use the corporate risk management policy in the risk management approach for this project.
Is this appropriate, and why?

  • A. Yes, because experience from previous projects should be taken into account in the risk management approach.
  • B. Yes, because the corporate risk management policy was updated, as a result of lessons from previous projects.
  • C. No, because the risk management approach should be tailored to suit the project and its environment.
  • D. No, because a separate risk management approach is not necessary when the company has a risk management policy.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: C
C. No, because the risk management approach should be tailored to suit the project and its environment. Refer 3.7 If PRINCE2 is not tailored, it is unlikely that the project management effort and approach would be appropriate for the needs of the project.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
The correct answer is B. Yes, because the corporate risk management policy was updated, as a result of lessons from previous projects. In PRINCE2, learning from experience is a fundamental principle. The corporate risk management policy was refined based on experiences from a similar project. Using this updated policy in the risk management approach for the current project is appropriate as it incorporates lessons learned from past experiences. However, it’s also important to tailor the approach to suit the specific context and environment of the current project
upvoted 1 times
ravi_aws
1 year, 1 month ago
Option A is not the best choice because it doesn't explicitly mention that the corporate risk management policy was updated based on previous project experiences. While using past project experience is generally valuable, it's crucial that the policy has been refined and improved based on those experiences, as stated in option B.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.