Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 11 question 19 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 19
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

The delivery of the pilot courses has been split into two separate products: 'planned pilot courses' and 'delivered pilot courses'. 'Planned pilot courses' will be produced during stage 3, and the 'delivered pilot courses' will take place during stage 4. This will allow the project board to approve the plan for the pilot courses before the resources are committed to delivering the pilot courses.
Why is this an appropriate application of the plans theme to control the project?

  • A. Because a PRINCE2 project should focus on the quality of the products being delivered.
  • B. Because the pilot courses have been broken down into two separate products.
  • C. Because the project board should ensure that lessons from one stage are applied to the next stage.
  • D. Because the delivery steps to create the pilot courses have been aligned to the management stages.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: D
D seems to be the most apocopate option amongst the all.
upvoted 1 times
ManikRoy
11 months, 2 weeks ago
Refer Page 103 - The ends of management stages do not necessarily need to occur at the same time as the ends of delivery steps, but there are often benefits if they do.
upvoted 1 times
...
...
ravi_aws
1 year, 1 month ago
D In this scenario, splitting the delivery of the pilot courses into two separate products and aligning them to the management stages is an appropriate application of the ‘Plans’ theme. This allows for better planning, monitoring, and control of the project’s progress and quality. It also enables the project board to review and approve the plan for the pilot courses before committing resources to their delivery. This aligns with PRINCE2’s principle of ‘Manage by Stages’, where the project is planned, monitored, and controlled on a stage-by-stage basis
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...