Exam PRINCE2-Practitioner topic 11 question 16 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 16
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

DRAG DROP -

QUALITY -
Teams have been set up to develop different parts of the 'classroom-based training materials'.
Here are three activities related to managing quality.
Which role (A-F) should carry them out?
Choose only one for each activity. Each role can be used once, more than once, or not at all.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?).
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
1. Project Manager 2. Project Assurance 3. Senior User
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
If the product meets requirements, the Project Manager will "sign off" the product, which confirms acceptance. So 1. Project Manager 2. Project Assurance 3. Project Manager
upvoted 1 times
ravi_aws
1 year, 1 month ago
For 3. I would rectify the answer to senior user.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...