The project is in stage 2. The project manager is reviewing stage status and has collected the checkpoint reports from the team managers. These show that the products are being completed on schedule. However, project support has raised issues that quality reviews have not been completed as agreed. The project manager reports in the highlight report that the stage is progressing well.
Is this appropriate, and why?

  • A. Yes, because the highlight report is a summary of the information in the checkpoint reports.
  • B. Yes, because the highlight report is used to provide the project board with stage and project progress.
  • C. No, because the project manager should have recorded the cause of the delay to the quality reviews in the lessons log.
  • D. No, because the issues raised by project support are a cause for concern and should be reflected in the highlight report.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
The correct answer is D. No, because the issues raised by project support are a cause for concern and should be reflected in the highlight report. In PRINCE2, a highlight report is used to provide the Project Board with a summary of the stage status at regular intervals. This includes information on all major aspects of the project, such as the progress of work packages, risks, issues, and quality. In this scenario, while the checkpoint reports indicate that products are being completed on schedule, project support has raised issues regarding quality reviews not being completed as agreed. This is a significant concern that could impact the quality and success of the project. Therefore, it’s important that such issues are accurately reflected in the highlight report.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...