Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 11 question 9 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 9
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the 'e-learning course' has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.
Is the team manager's response appropriate, and why?

  • A. Yes, because a supplier may want to keep the details of the specialist work confidential.
  • B. Yes, because team plans are mandatory on a project of this size and complexity.
  • C. No, because the project manager needs detailed plans to manage the work of several teams.
  • D. No, because the team plan must be submitted to project assurance to check it is viable.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: A
Refer Page 238 Seek necessary approval for the team plan (although in a commercial customer/supplier relationship it may be inappropriate for the project manager to review and approve the team plan and, in such a context, the senior supplier may review and approve the team plans)
upvoted 2 times
...
ravi_aws
1 year, 1 month ago
C is the correct answer. No, because the project manager needs detailed plans to manage the work of several teams. The project manager has responsibility for coordinating and directing the work of all teams delivering products in the stage. To exercise effective control, the project manager needs to review and approve the detailed plans for each team's work.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...