Exam PRINCE2-Practitioner topic 11 question 7 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 7
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

CLOSING A PROJECT -
Benefits relating to income and business reputation after the project has closed cannot be shown at project closure.
Which statement describes how the 'closing a project' process makes provision for this?

  • A. As part of the 'prepare planned closure' activity. It will be confirmed that the project has delivered what was defined in the project product description.
  • B. As part of the 'prepare planned closure' activity. It will be confirmed that the acceptance criteria defined in the project product description have been met.
  • C. As part of the 'hand over products' activity, the benefits management approach will be updated to include future activities for benefit measurement.
  • D. As part of the 'hand over products' activity, the 'finalized materials' will be passed to the operational business environments.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?).
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: C
Agree with Answer C As part of the 'hand over products' activity, the benefits management approach will be updated to include future activities for benefit measurement.
upvoted 1 times
ManikRoy
1 year, 1 month ago
refer 20.4.3 Check that the benefits management approach includes post-project activities to confirm benefits that cannot be measured until after the project's products have been in operational use for some time
upvoted 1 times
...
...
ravi_aws
1 year, 1 month ago
C. As part of the 'hand over products' activity, the benefits management approach will be updated to include future activities for benefit measurement. In this statement, it acknowledges that benefits related to income and business reputation may extend beyond the project closure. Therefore, the benefits management approach is updated during the 'hand over products' activity to include future activities for measuring these benefits.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted