Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 11 question 6 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 6
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

All the products that are due in stage 3 have been completed, apart from the 'updated corporate quality procedures'. The work has been completed but the product has not yet been approved. The executive has been told that it will be signed off before the end of the project. In response to an exception report, the executive has instructed the project manager to plan to obtain approval of the product in stage 4.
Is this appropriate application of the report management stage end' activity, and why?

  • A. Yes, because approval of the product can be carried forward into the next stage, with authority from the project board.
  • B. Yes, because the completion of the product in the next stage is a follow-on action recommendation for stage 4.
  • C. No, because approval of the products was planned for stage 3 and must be completed before the stage ends.
  • D. No, because a project-level exception plan is required before approval of the quality procedures can be delayed.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?).
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Agree with the option A as it seems logical.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
Option A is correct because approval of the product can be carried forward into the next stage, with authority from the project board. The End Stage Report should contain a forecast for the next stage, which will help the Project Board decide whether to continue the project or not
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...