Question #: 4
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

MANAGING A STAGE BOUNDARY -
The ABC Company trainers have been accredited and the course booking procedures have been amended. The 'managing a stage boundary' process is taking place at the end of stage 3.
Which activity should occur during the 'update the business case' activity?

  • A. Update the overall plan with the time and cost taken to develop the 'e-learning course' and 'amended course booking procedures'
  • B. Break the 'planned pilot courses' down into component products in order to identify the work required to deliver them.
  • C. Review whether the possible sales of the training course to external companies are likely to cover the project costs.
  • D. Review whether a new team manager should be appointed to lead the delivery of the pilot courses during stage 4.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?).
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: C
Option C is correct as it reviews the business justification of the project to understand if the project is still cost effective i.e. if the project is still desirable.
upvoted 1 times
ManikRoy
1 year, 1 month ago
refer 19.4.3 Examine & review 2nd point the impact of approved changes as these may affect the projected benefits
upvoted 1 times
...
ManikRoy
1 year, 1 month ago
It also does mention to review and examine the Project Plan but doesn't mention if it needs to be updated in this process/activity. Review & Examine - the project plan to see whether the final implementation date of the project has changed (to earlier or later), which might affect some or all of the projected benefits the project plan to see whether the cost of delivering the project's products has changed, which may affect the cost-benefit analysis
upvoted 1 times
...
...
ravi_aws
1 year, 1 month ago
In the scenario, reviewing whether the possible sales of the training course to external companies are likely to cover the project costs falls under this activity. This is because it involves assessing the financial viability of the project, which is a key aspect of updating the Business Case2. So, option C) is most appropriate for this situation.
upvoted 2 times
ravi_aws
1 year, 1 month ago
C is the best answer
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...