Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 11 question 3 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 3
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

The project is now closed. The expected increase in revenue is not being achieved. It has been agreed with the team manager for the 'marketing materials' that additional marketing activities will be undertaken to achieve the expected increase in revenue.
Who should be responsible for monitoring the results of the marketing activities, and why?

  • A. Senior user, because this person is responsible for realizing the benefits post-project.
  • B. Senior user, because this person is responsible for specifying the desired from the project.
  • C. The team manager for the 'marketing materials', because this person has the skills to demonstrate that the activities are effective.
  • D. The team manager for the 'marketing materials', because the project board is disbanded at the end of the project.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
A. Senior user, because this person is responsible for realizing the benefits post-project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...