Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 11 question 1 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 1
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

Based on lessons from previous projects that used the ABC Company standard development model, the project board has set low cost and time tolerances for stage 2. As a result, the project manager plans to set very low tolerances for time and cost for all work packages to be carried out during stage 2.
Is this an appropriate application of the 'manage by exception' principle, and why?

  • A. Yes, because the project manager should set tolerance equally for all work packages in a stage.
  • B. Yes, because setting appropriate tolerances for work packages will help keep the stage within tolerances.
  • C. No, because tolerances set by the project manager should be the same as those set by the project board.
  • D. No, because the project manager should divide the stage tolerances between the team managers.
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: B
Agreed with option B as the other 3 options are clearly incorrect.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
B So, while each work package might have different requirements and complexities, setting appropriate tolerances for each one (as per option B) will help keep the overall stage within its set tolerances1. This aligns with the PRINCE2 principle of 'Manage by Exception’1, which aims to provide an efficient way of governing a project by defining clear tolerances for project objectives.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...