Question #: 12
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

The Work Package has been in progress for four weeks and has four weeks remaining. The Information Technology Team Manager is concerned that he has no idea what the service provider is doing about preparing to accept the transfer of Information Technology equipment and staff. He is uncertain about what should be happening.
Which 2 initial actions should the Team Manager take in response to this concern?

  • A. Notify the Project Manager by raising an Exception Report.
  • B. Raise this concern in the next fortnightly Checkpoint Report.
  • C. Check the Communication Management Strategy to ascertain what records of communications with the service provider are required.
  • D. Check the Information Technology Work Package for development interfaces to see whether the service provider Team Manager should have been liaising with the Information Technology team during development.
  • E. Raise an issue to notify the Project Manager of this concern.
Show Suggested Answer Hide Answer
Suggested Answer: DE 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: DE
Agree with the answer D & E. A can NOT be correct as creating exception report is not duty of Team Manager. B also NOT as the TM should not wait that long to highlight a risk. C also NOT as TM gets all details from WORK package and is not supposed to check any other management documents. So checking work package for development interface and raising an issue to notify the Project Manager are correct options.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
C and D It is important to note that options A, B, and E are not the most appropriate initial actions in this situation. Notifying the Project Manager by raising an Exception Report may be premature without first gathering more information and understanding the situation. Raising the concern in the next Checkpoint Report may not provide immediate attention to the issue. Raising an issue to notify the Project Manager of the concern may be appropriate, but it should be done after conducting the necessary checks and gathering relevant information.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...