Question #: 3
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

Which of the following is NOT a trigger for the project manager to authorize a work package?

  • A. Stage Authorization
  • B. Corrective Action
  • C. Exception plan approved
  • D. Reporting highlights
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Old_Jedi
9 months, 4 weeks ago
B - corrective action
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
B Corrective action is not a trigger for the project manager to authorize a work package. Corrective action is taken when there is a deviation from the plan or when a problem arises that needs to be addressed
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...