Which is a minimum requirement for the “quality” theme?

  • A. Lessons must be used to inform the definition of quality expectations
  • B. A communication management approach must be produced and maintained
  • C. A benefits management approach must be produced and maintained
  • D. An issue register must be maintained for quality issues including off-specifications
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 1 day ago
Mod please change this is confusing to learn.
upvoted 1 times
...
Examcollectorthanos
1 week, 1 day ago
A is correct; Why the other options are not the minimum: B. A communication management approach must be produced and maintained: While important for communication, this is not specifically related to the Quality theme. C. A benefits management approach must be produced and maintained: This focuses on benefits realization, not the core of the Quality theme. D. An issue register must be maintained for quality issues including off-specifications: While important for tracking issues, the minimum requirement is about proactively using lessons to define quality expectations.
upvoted 1 times
...
Kjennset
3 weeks, 5 days ago
Selected Answer: A
This is a minimum requirement for the "quality" theme in PRINCE2, ensuring that past experiences help set clear quality criteria for the project.
upvoted 1 times
...
Ppp333
1 year, 2 months ago
Selected Answer: A
8.2 PRINCE's requirement for quality Use lessons to inform quality planning, the definition of quality expectations and quality criteria (PRINCE2’s learn from experience principle).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...