B. As a minimum, the project board should receive oral reports from the project manager.
The 'directing a project' process in PRINCE2 is responsible for the overall direction and management of the project. The purpose of this process is to ensure that the project remains aligned with the organization's objectives, and that the project is delivering the expected benefits.Option A-While the project board can use information from the information radiator, it is the responsibility of the project manager to provide regular reports to the project board.Option C - While the project board can attend the delivery team's daily stand-up meetings, it is not a requirement of the 'directing a project' process.Option D -While the project board should receive regular reports on the project's progress, these reports should focus on the project's overall status, including progress against the plan, issues and risks, and benefits realization. The project board should also receive reports on cost and time overruns, but these should not be the sole focus of the reports.
upvoted 4 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Djtomip
1 year, 2 months ago