While preparing the Quality Management Strategy, the Project Manager noticed that the corporate quality management system does not specifically cover project management. Which option provides an appropriate way for the Project Manager proceed?
A.
Record the development of a corporate quality management system for project management as a prerequisite of the Project Plan.
B.
Proceed with the project without a Quality Management Strategy and adopt the selected service provider's standards in stage 4.
C.
Seek relevant organizational standards, then facilitate a workshop to discuss the Quality Management Strategy with Project Assurance.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SantiagoAregentina
1 year, 2 months ago