Exam PRINCE2-Practitioner topic 9 question 15 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 15
Topic #: 9
[All PRINCE2-Practitioner Edition 6 Questions]

While preparing the Risk Management Strategy, the Project Manager considered the commercial customer/supplier environment and how this may affect the management of risk. Which approach should the Outsourcing project adopt?

  • A. Plan to use the selected service provider's risk management procedures.
  • B. All project risks associated with the specialist deliverables should be owned by the selected service provider.
  • C. Due to the sensitive nature of this project, consideration should be given to creating a separate Risk Register to be held by MFH and the selected supplier.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: C
Refer 10.3.6 Commercial Consideration In a commercial context there may be a need for more than one risk register as some project risks could be unique to only one party, with good reasons for them not to be visible to the other party.
upvoted 2 times
...
ravi_aws
1 year, 1 month ago
A. Plan to use the selected service provider's risk management procedures. In an outsourcing project, it is common to leverage the risk management procedures and expertise of the selected service provider. This approach can be beneficial because the service provider often has experience and established processes for managing risks associated with the services they provide. By planning to use the service provider's risk management procedures, you can tap into their knowledge and resources to identify, assess, and mitigate risks effectively. It also ensures that the risk management efforts are aligned with the specifics of the outsourced services.
upvoted 1 times
...
SantiagoAregentina
1 year, 2 months ago
Selected Answer: C
Also think it is "C"
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...