While planning the initiation stage, the Project Manager reviewed some threats that had been recorded in the Daily Log. Which threat should have been assessed for possible risk responses to be included in the Initiation Stage Plan?
A.
MFH has no experience in outsourcing and this may affect understanding of what is required, resulting in inadequate plans and strategies.
B.
The Project Brief is a complex document and may not be approved by the Executive.
C.
There is a shortage of service providers so there is a possibility that no suitable service providers respond to the request for proposals. This would prevent the Outsourcing project from proceeding.
This threat is appropriate for assessment and inclusion in the risk responses within the Initiation Stage Plan. It represents a significant risk that could impact the project's ability to proceed with outsourcing if no suitable service providers respond. Therefore, it's important to assess this threat and plan appropriate risk responses, such as identifying alternative actions or contingency plans in case this risk materializes.
upvoted 2 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SantiagoAregentina
1 year, 2 months ago